Little Rock, AR · Local contractor rules
Contractor license requirements in Little Rock, Arkansas
What Little Rock requires before you work there, on top of Arkansas state licensing. Checked November 6, 2026 from 5 official sources.
Do I need a Little Rock license to work there?
Only for some trades: Electrician.
The Little Rock license
Electrical contractor registration For: Electrician FeeNot publishedBond$10,000This is on top of the Arkansas state license, if your trade has one. Check your trade
Pick your trade
Find your work below. Each row shows whether you need an Arkansas state license and which Little Rock license is yours. Open a row for the full checklist.
For all contractors, the permit desk requires a copy of the Arkansas contractor license, a copy of the city business license, and a $10,000 surety bond made out to the City of Little Rock, which may be obtained from any bond or insurance company.1
How to start working in Little Rock
- 1
Get your Arkansas license if your trade needs one
Arkansas licenses some trades and not others. The trade list above shows the state rule for yours.
- 2
Get a surety bond
$10,000Little Rock requires a $10,000 bond.3 You pay a yearly premium to a surety company, not the full amount. Estimate the cost
- 3
Apply for your Little Rock license
Apply with City of Little Rock Department of Planning and Development, Building Codes Division. Bring the bond and insurance certificate.
- 4
Business license or tax registration
City ordinance requires a City Contractor's License (city business license, also called a privilege license) to operate in Little Rock.14
More
Business licenses are handled by the city's Treasury Management Division and renew each year on January 1. Unpaid licenses get a 10% penalty after February 1, another 10% after March 1, and 30% in total penalties after April 1.
- 5
Pull a permit for each job
Construction permits are obtained by the owner, the general contractor or their agent at the Building Codes Division, 723 West Markham Street, 2nd floor.235
More
Electrical permits are issued only to people licensed under the city electrical code, unless the person has a permanent employee who is a licensed journeyman electrician. Separate permits are required for gas, plumbing and HVAC work.
Little Rock license details
Electrical contractor registration Electrician Fee— Bond$10,000
Who needs it
Any person or firm that engages in the business of electrical contracting must register its name, residence and place of business with the Building Codes Division permit section.3
More
No one may install, alter or repair electrical wiring or equipment without a valid license approved by the Electrical Inspection Supervisor.
What you need
The registration must name the master electrician who manages or supervises the business and the date that person qualified as a master electrician.3
Every person must pass an examination held by the Arkansas Board of Electrical Examiners before doing electrical business in the city.3
A master electrician may represent only one firm at a time. If the master electrician leaves and is not replaced within 3 days, the contractor's license is suspended until a new master electrician is employed.3
Changes of business location, company name or master electrician must be reported to the permit section right away.3
Licenses must be displayed at the place of business, and contractor vehicles must show the company name on each side in letters at least 2 inches high.3
Fees and bond
A $10,000 surety bond to the City of Little Rock is required before an electrical permit is issued.
Before a permit is issued, the contractor gives the permit desk a copy of the Arkansas contractor license, a copy of the city business license, and a $10,000 surety bond made out to the City of Little Rock.1
Special trades also give copies of their master plumbing or master electrical license, or a Class A mechanical license.1
Electrical contractors must register with the Building Codes Division permit section, naming the master electrician in charge.3
For homeowners
Can I do the work and pull the permit myself?
A homeowner may get an electrical permit for work on their own home if they hold a current Arkansas master or journeyman electrician license, or pay a $35 consultation fee.3
More
The homeowner must prove they own the home and live or will live in it, consult with the Electrical Inspections Supervisor about the project and their competence, and sign a statement agreeing to follow the electrical codes. The fee is not refunded if the homeowner is found not competent, and the city may require a licensed electrician after two rejected inspections.
Check a contractor before you hire
Little Rock requires contractors to hold a local license or registration and a bond. Ask for a copy of each.
Good to know
Individuals licensed or registered by the Arkansas HVACR Licensing Board may make electrical connections to heating and air-conditioning units without another license, if a suitable disconnect provided by others is within 10 feet of the unit.3
Common questions
Do I need a contractor license to work in Little Rock?
Only for some trades: electrician. Other trades need no Little Rock license, only any Arkansas license the trade requires.
Do Little Rock contractors need a bond?
Yes. Electrical contractor registration: $10,000 bond.
Can a homeowner pull a permit in Little Rock?
A homeowner may get an electrical permit for work on their own home if they hold a current Arkansas master or journeyman electrician license, or pay a $35 consultation fee. The homeowner must prove they own the home and live or will live in it, consult with the Electrical Inspections Supervisor about the project and their competence, and sign a statement agreeing to follow the electrical codes. The fee is not refunded if the homeowner is found not competent, and the city may require a licensed electrician after two rejected inspections.
Sources
5 official pages, checked November 6, 2026
- Documents Required to Be Submitted Before a Permit May Be Issued (030212) · City of Little Rock, Building Codes Division · checked 2026-11-06
- Commercial Construction Information · City of Little Rock, Building Codes Division · checked 2026-11-06
- Little Rock Code, Article III, Electricity (Electrical Code) · City of Little Rock, Department of Planning and Development · checked 2026-11-06
- Starting a Business in Little Rock: Obtaining Permits and Licenses · City of Little Rock, Finance · checked 2026-11-06
- Application for Electrical Permit (Rev. 1-20) · City of Little Rock, Building Codes Division · checked 2026-11-06
Rules change. Confirm with the agency before you bid or start work. How we research